Two river bridges along evacuation road with improved erosion and landslide protection standard

East-Timor - Temporary

Created at: 15 May 2022

Description

  1. Two bridges built along evacuation road of 2m heights and with spans of 3.9m and 4.6m, allowing safe access for vehicles, pedestrians and animals during all conditions

  2. Gabions, reinforced concrete and masonry used around foundations to protect bridges from river erosion

  3. Approximately 3m3 of local eucalyptus urophylla timber decking securely fastened on each bridge

  4. Safety rails installed

Help us provide more detailed information about this project by contributing!

About the author

Geert Westerhuis

• Submitted 227 projects
• Expert at Water
• Netherlands

View all 227 projects by this author →